Grand Valley State University Science Lab, Classroom, and Office Building

New construction; Grand Valley State University Science Lab, Classroom, and Office Building; Fishbeck, Thompson, Carr and Huber Inc.

08/15/2013


This image shows the rendering of the Grand Valley State University project. Courtesy: Fishbeck, Thompson, Carr & HuberEngineering firm: Fishbeck, Thompson, Carr & Huber Inc.
2013 MEP Giants rank:
99
Project:
Grand Valley State University Science Lab, Classroom, and Office Building
Address:
Allendale, Mich., United States
Building type:
School (college, university)
Project type:
New construction
Engineering services:
Automation & Controls, Electrical/Power, HVAC, Lighting
Project timeline:
September 2011 to May 2015
Engineering services budget:
N/A
MEP budget: $964,304

Challenges and solutions

Understanding that lab buildings are typically large energy consumers, FTC&H tailored the mechanical design to utilize energy efficient systems and equipment. Some of the strategies included ventilation control through an active contaminant monitoring system, heat recovery/exchange between exhaust and fresh airstreams, occupancy control of terminal unit zone controls, and use of an auxiliary heat recovery chiller to efficiently handle simultaneous heating and cooling loads within the building.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.