FedEx Field Solar Array

Large-scale solar array: FedEx Field Solar Array; DLR Group

Source: DLR Group

08/09/2012


Click to watch the Timelapse of NRG's Solar Panel Installation at FedExField video. Courtesy: DLR Group and YouTubeProject name: FedEx Field Solar Array

Location: Landover, Md.

Firm name: DLR Group

Project type, building type: Large-scale solar array, stadium

Project duration: 4 months

Project completion date: Sept. 11, 2011

Engineering challenges

DLR Group teamed with NRG Energy to design a large-scale solar array at FedEx Field, home of the Washington Redskins. The 8,000-panel, 2 MW photovoltaic energy generating system covers 800 parking spaces DLR Group’s design at FedEx Field is a 2 MW photovoltaic energy generating system. A branded entry plaza for client NRG Energy also is a focal point of the design. Courtesy: DLR Group (Click to enlarge)and generates enough power to serve all of the facility’s electrical needs on non-game days. It also provides a portion of the stadium's electricity needs on game days. The prominent display of solar panels raises awareness of renewable energy. A branded entryway showcases clean energy technologies and additional information about the potential of renewable energy. A signature design element is a 30-ft-tall silhouette of a quarterback dubbed “Solar man” that showcases the flexibility of thin-film solar technology. The biggest challenge for the design of the FedEx Field solar array was the tight construction schedule. The design launched on May 1, 2011. Construction commenced on July 7, with a hard completion date of Sept. 11, which was the home opener for the Washington Redskins versus the New York Giants. The date also marked the 10-year anniversary of the 9/11 tragedy. The Giants and Redskins represented the two cities most directly affected by 9/11. The eyes of the nation were to be on FedEx Field that day so it was essential to meet the project schedule.

Project schedule

  • 05/01/2011: Design commences
  • 07/05/2011: Construction starts
  • 09/11/2011: Washington Redskins season opener vs. New York Giants
  • 09/18/2011: Solar Bowl, official grand opening, Washington Redskins vs. Arizona Cardinals

The design of the NRG Entry Plaza at FedEx Field features 188 BIPV translucent solar panels applied to the exterior wall of a pedestrian entry ramp. Solar Man is a 30-ft-tall statue using thin-film solar laminated between two layers of colored polycarbonate. Courtesy: DLR Group (Click to enlarge)

Solutions

The integrated DLR Group engineering (structural and electrical) and architecture team worked strategically to ensure project delivery by communicating directly with manufacturers to address and refine technical specs to achieve the performance needs for panels during design. By developing early relationships with Prince Georges County, the design team was able to phase the review and permitting process to allow construction to start prior to receiving all permits. Construction also was expedited by collaborating with panel manufacturers to time the delivery of materials to the site on specific dates to avoid storage and movement of panels prior to installation. Panels literally arrived, were unloaded from the truck, and were immediately installed. The project also includes 10 electric vehicle charging stations from NRG’s eVgosm charging network. Information kiosks in the parking lot and at the NRG entry plaza also inform fans about renewable energy and showcase NRG clean energy solutions. Construction was complete for the Redskins kick-off on Sept. 11, and for the official unveiling of the array during the Solar Bowl one week later.

Project facts

  • System size: 2 MW dc—1,957,728 W actual
  • Estimated annual energy production: 2.5 million kWh/year; 2,500 MWh/year— 2,581,193 kWh/year ‚ actual—8,544 kWh/year (average metro Washington, D.C., home)
  • Panels: 8285 total solar panels, 7572 parking lot panels (SunPower 235 monocrystalline panels), 525 ramp roof panels (SunPower 235 monocrystalline panels), 188 ramp wall panels (Schott ASI semitransparent laminate panel)
  • Parking lot solar array: 841 covered parking spots, 2.47 acres (107,400 sq ft) of parking spots physically covered (parking spaces only)
  • Electric vehicle charging stations: 10 total Level 2 charging stations

The 188 BIPV translucent solar panels on the entry ramp wall are backlit with programmable Traxon LED light fixtures. Courtesy: DLR Group (Click to enlarge)SunPower 240 Monocrystaline Panels provide 800 covered parking spots on 2.5 acres at the FedExField array. Courtesy: NRG Energy (Click to enlarge)



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Integrating lighting, HVAC systems, Energy codes and lighting, BIM and fire protection engineering
Engineering hospital electrical systems, Boilers and boiler systems, Building envelope best practices
Hospital indoor air quality, ASHRAE 90.1 update, Specifying piping materials, Integrated project delivery
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Preventing arc flash, Backup power fuel choices, power for high-tech facilities
Using BIM in electrical power design; Closed-transition transfer; Medium-voltage distribution; Diesel emission regulations; Increasing emergency power capacity

Poll of the Week

When engineering systems in military buildings, what’s the most difficult issue you face?
Automation and controls
Codes and standards
Electrical and power
Energy efficiency, sustainability
Fire and life safety
HVAC


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.