February 12 Southland Industries update: Hospital Levels 2, 4, 5, and 6 being roughed-in; South Clinic Level 1 drywall installation; Parking garages underway

Hospital Levels 2, 4, 5, and 6 being roughed-in; South Clinic Level 1 drywall installation; Parking garages underway

By Gary Lovewell, LEED AP BD+C February 12, 2014

As of Feb. 12, 2014:

  • Currently roughing-in systems on Levels 2, 4, 5, and 6 in the hospital. Basement and Levels 1 through 4 have drywall wall installation underway.
  • The West Clinic has ceilings and diffusers being installed, the North Clinic is roughed-in and awaiting paint and ceilings. The South Clinic has drywall being installed on Level 1 and rough-in is underway on Level 3.
  • All three parking garages are underway.