Fairview Health Services Proves the Value of "the Matrix"

07/01/2006


As an integrated health-care system, Fairview's six community hospitals, academic medical center, children's hospital, 31 primary care clinics, 25 specialty clinics, four urgent-care clinics and specialty service centers across the state of Minnesota provide a complete range of health-care services.

In partnership with University of Minnesota Physicians, Fairview plans to open the Maple Grove Outpatient Specialty Care Center in 2007, a 135,000-sq.-ft. specialty care center that comprises six operating rooms, a diagnostic center, a cancer center and outpatient clinic.

Fairview, Walker and Assocs.—the owner's representative—and the M/E/P firm, Hammel, Green and Abrahamson, Inc., Minneapolis, decided that the mechanical systems and equipment would be dedicated to serving the Phase I ambulatory care center, with space allotted for a central plant to house the heating plant, water-cooled chillers, cooling towers and other equipment to meet the future building's needs. The present system will then be tied into the central plant.

Fairview used an objective approach and decision-making matrix to select among four options for the mechanical system:

Option 1: Rooftop units (RTUs), with cooling provided by a refrigerant cooling coil, compressor and air-cooled condensing unit; gas-fired heating; and ventilation in one package; with screening.

Option 2: Improved RTUs with an integral hallway for each RTU to provide better access to the roof and enable maintenance to be performed indoors.

Option 3: Rooftop-level air-handling units (AHUs) providing ventilation, with cooling provided by a cooling coil and basement-level chiller, and heating provided by a heating coil and basement-level boiler.

Option 4: Similar equipment to Option 3, but with the AHU located in the basement, with shafts for outside air and relief air.

The building user group and members of HGA's project team identified and weighted 12 financial and performance criteria, which included several high priorities: patient and staff safety; patient and staff comfort; initial cost; energy efficiency/payback; flexibility for vertical expansion; and sustainable design. HGA developed early schematic designs of each of the four options, and Walker and Assocs. and Knutson Construction Services, Minneapolis, developed construction estimates.

Option 1 offered the lowest initial cost, fast installation and a single equipment package, but came with higher life-cycle costs, lower energy efficiency and increased labor cost for maintenance when compared with the other options. Option 2 offered a moderate initial cost, with lower maintenance costs and higher-quality equipment, yet energy efficiency and life-cycle costs remained drawbacks. Option 3 offered better life-cycle costs than Options 1 or 2, yet it was the most expensive and reduced future flexibility for vertical expansion.

The decision-making process was complicated by the prospect of the Phase II addition. The group recognized that Options 1 and 2 were priced to qualify as "throwaway" systems when Phase II is implemented, but not Option 3. Moreover, if Phase II were to be built above Option 3, potentially costly structural modifications would be required.

The user group, project team, architect and Fairview executive-level leaders ultimately chose Option 4 because it combined reasonable initial cost, good life-cycle cost and flexibility.

Criteria

Weight

Option 1: Rooftop units

Option 2: Rooftop units w/access

Option 3: Penthouse AHUsw/central plant

Option 4: Mech. room w/central plant

Patient comfort and safety

25%

2

2.7

2.7

2.7

Flexibility and future growth

25%

1

2.5

2.5

4

Low first cost

25%

4

2

2

2

Energy efficiency

10%

1

3

3

3

Maintainability

5%

1

2

3

4

Aesthetics

5%

1

1

3

5

Integration w/floor plan

5%

3

3

3

1

Total unweighted

13

16.2

19.2

19.6

Total weighted

2.1

2.4

2.5

3





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me