Evaluating a Grounding System

The Shuttle Avionics Integration Laboratory (SAIL) in Huntington Beach, Calif., was designed with an isolated single-point earth grounding system, which best simulates a vehicle in flight while protecting laboratory personnel against shock and equipment faults. The test configuration is as close to an operational space shuttle as possible and reduces the electromagnetic interference envir...

06/01/2001


The Shuttle Avionics Integration Laboratory (SAIL) in Huntington Beach, Calif., was designed with an isolated single-point earth grounding system, which best simulates a vehicle in flight while protecting laboratory personnel against shock and equipment faults. The test configuration is as close to an operational space shuttle as possible and reduces the electromagnetic interference environment in the SAIL facility. Controls are in place to prevent the isolated single-point grounding system from causing safety hazards.

A new single-power transformer dedicated to the SAIL area was installed to replace three existing transformers and improve the fidelity of both the power quality and the grounding within SAIL. Although this new hardware installation conflicts with the SAIL ground isolation requirements, it conforms to the National Electrical Code (NEC), 1990 edition.

In conjunction with the new installation, engineers from Spencer Engineering, Carmel, Ind., and facility engineers from the National Aeronautics and Space Administration proposed tying the isolation transformer secondary wye neutral as well as the master electrical common connection assembly to the facility ground, thus creating a non-isolated single-point grounding system.

A grounding system evaluation was performed to verify that the new SAIL grounding configuration was electromagnetically compatible. All isolated grounds, even a single-point ground, pose a potential hazard during a lightning strike.

The evaluation examined areas such as effects of the non-isolated single-point ground to the SAIL in terms of electromagnetic interference (EMI). Knowledge of EMI noise under two different single-point ground conditions was a "threshold test" for approving the system.

From Pure Power, Summer 2001.





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me