Emulation, beyond simulation, for motion control

Get to market in half the time using emulation, even with highly complex motion control installations.

03/08/2013


Polytron emulation helped with an overhaul of 4 miles of conveyors, with 95% debugging before onsite installation, 11 new tie-in points, four new PLCs, and modified programming in three existing PLCs. Courtesy: PolytronYou need to increase capacity, so you’re adding a new line. Maybe you want to bring outsourcing inside, gear up for a new product launch, or rearrange your geographical footprint to lower distribution costs. Either way, every day without that new line is another day of lost revenue. What do you do?

Testing a new controls system off-site using emulation can get a new line up and running at capacity in half the time, for half the cost, with half the effort. System integrator Polytron achieved such results in a highly complex consumer products installation. The plant needed another line that would lead to a new high-speed palletizer, including:

• A maze of conveyors 4 miles long that would need to be overhauled with 11 new tie-in points.

• Multiple decision points, along with integration with some systems that were three years old and others that were nearly 30 years old.

• Four new programmable logic controllers (PLCs), plus modifications to three existing PLCs.

The line had to be at capacity as soon as possible, since the customer already had demand for everything it could make. Until the new line reached capacity, vital revenue was missing.

Cut start-up time in half

Polytron designed, programmed, and debugged the new controls system off-site using its emulation tools. Unlike traditional systems with field debugging, these control programs were 95% debugged on day one, leading to much faster start-up and lower costs. On-site time was reduced by 10 weeks to half the time it would’ve taken to perform a traditional start-up. After three days of start-up, the new line ran at 80% of capacity.

Simulation just checks code inside the PLC. Emulation requires the controls system to operate a computer model of the installed system in real time, just as if it were running the new system on the plant floor, which allows 95% debugging and verification before site installation. Running a computer model of the system is more powerful than running the system in the field because emulation can address more variables and yield more useful data in less time. It lets an engineer run different scenarios without impacting real production.

Emulation allows test running a new bottle size, or package format, and finding out how the line will operate, without losing production time on the running line. Imagine testing 10 years of forecasted production on a finished goods handling system. Emulation makes that possible.

- Brent Stromwall is vice president, Polytron. Edited by Mark T. Hoske, content manager, CFE Media, Control Engineering, mhoske(at)cfemedia.com.

www.polytron.com 

More details from Polytron about:

- Using emulation 

- Instant project start-ups 

Select an integrator from the Control Engineering Automation Integrator Guide



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.