Emulation, beyond simulation, for motion control

Get to market in half the time using emulation, even with highly complex motion control installations.

03/08/2013


Polytron emulation helped with an overhaul of 4 miles of conveyors, with 95% debugging before onsite installation, 11 new tie-in points, four new PLCs, and modified programming in three existing PLCs. Courtesy: PolytronYou need to increase capacity, so you’re adding a new line. Maybe you want to bring outsourcing inside, gear up for a new product launch, or rearrange your geographical footprint to lower distribution costs. Either way, every day without that new line is another day of lost revenue. What do you do?

Testing a new controls system off-site using emulation can get a new line up and running at capacity in half the time, for half the cost, with half the effort. System integrator Polytron achieved such results in a highly complex consumer products installation. The plant needed another line that would lead to a new high-speed palletizer, including:

• A maze of conveyors 4 miles long that would need to be overhauled with 11 new tie-in points.

• Multiple decision points, along with integration with some systems that were three years old and others that were nearly 30 years old.

• Four new programmable logic controllers (PLCs), plus modifications to three existing PLCs.

The line had to be at capacity as soon as possible, since the customer already had demand for everything it could make. Until the new line reached capacity, vital revenue was missing.

Cut start-up time in half

Polytron designed, programmed, and debugged the new controls system off-site using its emulation tools. Unlike traditional systems with field debugging, these control programs were 95% debugged on day one, leading to much faster start-up and lower costs. On-site time was reduced by 10 weeks to half the time it would’ve taken to perform a traditional start-up. After three days of start-up, the new line ran at 80% of capacity.

Simulation just checks code inside the PLC. Emulation requires the controls system to operate a computer model of the installed system in real time, just as if it were running the new system on the plant floor, which allows 95% debugging and verification before site installation. Running a computer model of the system is more powerful than running the system in the field because emulation can address more variables and yield more useful data in less time. It lets an engineer run different scenarios without impacting real production.

Emulation allows test running a new bottle size, or package format, and finding out how the line will operate, without losing production time on the running line. Imagine testing 10 years of forecasted production on a finished goods handling system. Emulation makes that possible.

- Brent Stromwall is vice president, Polytron. Edited by Mark T. Hoske, content manager, CFE Media, Control Engineering, mhoske@cfemedia.com.

www.polytron.com 

More details from Polytron about:

- Using emulation 

- Instant project start-ups 

Select an integrator from the Control Engineering Automation Integrator Guide



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
integrated building networks, NFPA 99, recover waste heat, chilled water systems, Internet of Things, BAS controls
40 Under 40; Performance-based design; Clean agent fire suppression; NFPA 92; Future of commissioning; Successful project management principles
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me