Do primary windings of liquid-filled transformers fail?

The short answer is no, primary windings of liquid-filled transformers don't fail. Here's why.

05/17/2012


VPI failure at ends of windings, and flashover to ground.In the same 35-year period of time, I’m counting up the number of failures of primary windings of liquid-filled transformers I’ve experienced, or have been reported to me, or that I’ve heard about or read about, caused by vacuum breaker switching in data centers. It’s exactly NONE.

In that same period of time, I’ve commissioned well over 500 liquid-filled transformers installed indoors and outdoors at large data centers, and have experienced zero primary winding failures, despite hundreds of deliberate switching operations of upstream vacuum breakers during commissioning and later plant operations, under all possible conditions of system loading and connection configurations in various primary loop arrangements. Nearly half of these had 34.5 kV primaries, as nasty and tough and ugly a utility distribution voltage as there is on the planet (more to come about system voltages and their relationship to the problem).

Again, I’m only relating my personal experiences and observations and opinions here. If anyone knows of failures of primary windings in liquid transformers installed in data centers caused by this phenomenon, I would like very much to learn about them.

Some Explanations for the Differences 

 

Clients ask me, “if you believe all of this so strongly, what logical reasons are there to explain these differences?”  Here are some of the reasons:

  • Of the 30 or more failures of dry-types I’ve personally investigated, approximately 20% of those were failures deep within the windings, suggesting oscillatory transients at the resonant frequency of the transformer, most likely caused by re-strike ignition phenomena during breaker opening at light transformer loading. (All of those failures coincidentally had secondary loads of 6 or 12 pulse input rectifiers in the front ends of static UPS systems).
  • But, the large majority of the failures I investigated occurred at the ENDS of the primary windings, or at delta corner jumper leads, or at tap connections, and often flashed over to the grounded steel enclosure or to grounded core steel. I’ve come to believe that a major part of the problem was the connections to these live parts were insulated only by air, and that arrangement provided an all-too-easy flashover path on seeing a sudden big blast of L(di/dt) come shooting out the ends of the windings.
  • Moreover, these failures occurred in areas where winding insulation was changing from paper to air-only, and where the line impedance was also chancing. Had all these connections been instead immersed under a high dielectric strength insulating fluid, I believe that many of these failures would not have occurred.
  • In other words, I think that a number of these failures might not have actually been WINDING failures. They were more likely terminal connection failures due to the inadequate dielectric strength of the surrounding air, and the actual winding damage that did occur might have been mostly just collateral damage. (Interestingly, the majority of these did not even have surge arresters of any type connected to the winding terminals). More discussion about this coming next week.


No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.