Data Center's Redesign Saves Money, Time

At its 20,000-sq.-ft. data center in Dallas, J.P. Morgan Chase handles an array of global financial services—with mission-critical requirements. Four 1,500-kW diesel generators operate in parallel on a common bus at the center. Two UPS systems, each consisting of two 375-kVA modules—with the ability to expand to four each—also operate in parallel on a common bus.

03/01/2002


At its 20,000-sq.-ft. data center in Dallas, J.P. Morgan Chase handles an array of global financial services—with mission-critical requirements.

Four 1,500-kW diesel generators operate in parallel on a common bus at the center. Two UPS systems, each consisting of two 375-kVA modules—with the ability to expand to four each—also operate in parallel on a common bus. Each UPS system feeds nine redundant 125-kVA static-switch power distribution units (PDUs).

A switchgear parallels the four diesel gensets, which are for standby power. A key software component allows facility operators to remotely monitor, control and even troubleshoot the gensets.

Lead times for orders of wet-cell battery strings were running at 28 weeks. Creative project scheduling led to immediate delivery of four strings of wet-cell batteries for the data center, but this meant keeping the batteries at a storage facility with the proper environment until needed.

Additionally, all switchgear requirements were bundled under one manufacturer. This required a new relationship to be forged between the switchgear and UPS makers.

Initial system requirements for the paralleling switchgear came up with a short-circuit rating of greater than 100 kiloamps interrupted current (kAIC)—not a "standard" rating—meaning longer lead times. The problem was solved by engineers who redesigned the switchgear to a lower kAIC rating that would still meet the data center's needs.

Reactors were installed in the neutrals of the diesel generators to limit their fault-carrying ability. A bus tie-circuit breaker was designed into the diesel paralleling gear. By controlling this breaker during any overlap transfer, the fault-carrying ability was limited. What's more, achieving a lower kAIC rating lowered the system's overall purchase price.

New generators had lead times of up to 20 weeks. Initially, the generator package included two refurbished generators and a new one—all three gensets sized at 1,750 kW, with the customer option to add a fourth. With Texas on the verge of utility deregulation, the firm was encouraged to look at the feasibility of exporting power back to the utility grid and set up its system to allow for that option.

As a result, the system design was switched to include the four 1,500-kW engine generators—with the supplier guaranteeing delivery dates. And the use of 1,500-kW, instead of 1,750-kW, units was another cost savings.

For more information on the project engineering capabilities of Encorp, circle number 451 on the Reader Service Card.

From Pure Power, Spring 2002.





Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
2017 MEP Giants; Mergers and acquisitions report; ASHRAE 62.1; LEED v4 updates and tips; Understanding overcurrent protection
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
Integrated building networks, NFPA 99, recover waste heat, chilled water systems, Internet of Things, BAS controls
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me