CSIA Best Practices offer project management planning guidance

The Control System Integrators Association Best Practices and Benchmarks covers the use of project plans, providing advice on project management, including the following tips.

03/27/2013


The Control System Integrators Association Best Practices and Benchmarks, now in its fourth edition, covers the use of project plans. Information below on project management was adapted from section 5.3 of the manual.

Develop a project management plan

The project management plan incorporates the output of other sales and planning processes, including:

  • Sales and client needs analysis
  • Proposal
  • Historical information related to project and client
  • Client’s and integrator’s organizational policies (e.g., required templates or forms)
  • Existence of client project execution methodologies and standards
  • Constraints and assumptions. 

Content should follow the integrator’s defined project planning methodology.

Review the project management plan with project members and then present the plan to the client.

Review the plan to ensure the execution process is understood and meets client expectations. The size and complexity of the project will determine the level and extent to which the plan will be reviewed. Ultimately, the review process allows for client buy-in and approval. Review and approval processes should follow those defined in the integrator’s project methodology. 

Hold a kick-off meeting with the client.

Review the plan

The integrator should review the project management plan with the client. If not already covered as part of the project plan review, be sure to address and agree upon:

  • Commercial issues
  • Scope of work and change order control method
  • Shipping requirements

Clarify expectations

During the kick-off meeting, clarify expectations by reviewing and addressing:

  • Project quality plan intentions
  • Project process intentions and client’s role
  • Items that require client’s signed approval
  • Configuration management requirements
  • Known project risks and a risk management plan
  • Format and content of physical deliverables
  • Roles and expectations during commissioning of the final product
  • Other general project execution issues.

Manage the project according to the project management plan.

Continuously manage and update the project baseline and other elements of the plan throughout the life of the project as status and requirements change. Any changes should be reflected in the project management plan. Monitor performance and take corrective actions based on the plan. 

Gain approvals along the way

Get formal approvals during project execution.

Some suggested key items for which to obtain approvals are:

  • Functionality and interfaces to be delivered (requirements and specifications)
  • Project technical risk plan and the associated contingencies
  • Project quality plan (including test plan)
  • Architecture and design reviews
  • User screen format, content, and navigation
  • Panel drawings for release to vendor
  • Resources, schedule, and scope changes.

Jeff Miller, PMP, is director of project management at Interstates Control Systems Inc., and chair of the CSIA Best Practices Committee.- Jeff Miller, PMP, is director of project management at Interstates Control Systems Inc., and chair of the CSIA Best Practices Committee. For more information about CSIA, visit www.controlsys.org. Edited by Mark T. Hoske, content manager, CFE Media, Control Engineering and Plant Engineering, mhoske(at)cfemedia.com.

Online Links

See related article on Collaboration, visibility key to successful project automation plan below.

www.controlsys.org 

www.interstates.com 



Sarah , , 11/25/13 03:40 AM:

great post! very informative. i've learned more about project planning strategies at http://pioneeripm.com/en/blog
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.