Commissioning commercial buildings

Ideally, all nonresidential buildings would be commissioned, and the team would start at the onset of the project. Because that’s not always the case, commissioning authorities and experts offer advice on building projects in various stages of commissioning, recommissioning, or retro-commissioning.


Left to right: Mark A. Gelfo, James I. Givens, Jim Huber, Brian Lindstrom, and Paul MeyerRespondents

Mark A. Gelfo, PE, LEED Fellow, GGP, CxA, EMP, Principal/Vice President, TLC Engineering for Architecture, Jacksonville, Fla.

James I. Givens, CxA, EMP, Division Manager, Field Services, RMF Engineering Inc., Baltimore

Jim Huber, CEM, CDSM, CMVP, LEED AP, NEBB CP, President, Complete Commissioning, Annapolis, Md.

Brian Lindstrom, PE, DCEP, National Director of Commissioning, Burns & McDonnell, Kansas City, Mo.

Paul Meyer, PE, CBCP, LEED AP, CEM, GBE, Senior Vice President, WSP, New York City

TLC and PSI commissioned the HVAC, lighting, and thermal envelope systems of University of Florida’s Heavener Hall Warrington College of Business building. Complex building systems need testing, fine-tuning, and ongoing commissioning to ensure ongoing buiCSE: Please describe a recent project you’ve commissioned.

Jim Huber: Some details of the project cannot be shared; however, it was a hangar facility on a military base in Delaware. The facility is approximately 66,000 sq ft, comprised of a large hangar bay, facility operations, and office space. The project was approximately 2 yr old and had never performed properly since the project turnover; we were brought on to do third-party commissioning of the mechanical systems. The commissioning effort was originally focused primarily on the HVAC systems (geothermal water-source heat pumps, water-to-water heat pumps, boilers, and air handlers), but eventually expanded to include the building enclosure.

Brian Lindstrom: We recently commissioned two new combined heat and power (CHP) plants with more than 40 MW of N+1-redundant capacity as part of a multiphase energy-performance program for a federal research campus in the Washington, D.C., metro area. Our work was in conformance with ASHRAE Guideline 0, U.S. Green Building Council LEED enhanced requirements, the GSA P100, and mission critical facility best practices for central utility plants that included functional testing, integrated systems testing, and black-start testing. Key equipment included natural gas combustion-turbine generators (CTG), heat-recovery boilers, absorption chillers, electric centrifugal chillers, steam chillers, thermal-energy storage tanks, heat-recovery steam generators (HRSG), diesel generators, and a balance of plant (BOP) control system.

Paul Meyer: The Plant and Animal Agrosecurity Research (PAAR) Facility is a highly secure biocontainment building. It is for conducting research with organisms that cause diseases in animals classified at biosafety level 3 (BSL-3 and BSL-3 Ag). It is also needed for working with plant diseases that could cause undue economic hardship on agriculture if released into the environment. PAAR is one of only two labs nationally with capacity for both plant and animal research at the BSL-3 and BSL-3 Ag safety levels. Ohio State University operates the BSL-3 facility on the Wooster campus, and it is the university’s first BSL-3 Ag facility. BSL-3 and BSL-3 Ag refer to safety guidelines established by federal law for conducting research with a variety of microorganisms. Under federal guidelines, all facilities handling potentially infectious agents must adhere to strict procedures to ensure containment of these pathogens. Depending on the ease with which microorganisms can be transmitted, they are classified as BSL-1, BSL-2, BSL-3, or BSL-4, with BSL-4 carrying the highest risk of infection. A BSL-3 Ag facility meets the standards for handling diseases of food-producing animals classified at the BSL-3 safety level.

The facility comprises:

  • 27,537 gross sq ft
  • Two BSL-3 enhanced laboratories and four BSL-3 Ag animal-isolation rooms that can handle large animals such as cows and pigs
  • Office, lockers and changing facility, decontamination areas, wash areas to clean cages, and a necropsy area for sample collection
  • Special airtight construction
  • Outgoing air is filtered through high-efficiency particulate air (HEPA) filters that trap microorganisms and prevent escape into other sections of the facility and the surrounding environment.

<< First < Previous 1 2 3 Next > Last >>

J.R. , TN, United States, 09/01/15 12:38 PM:

The more information provided the better for future users
Anonymous , 09/08/15 06:26 PM:

Excellent! Contractors need to read this so their D/B design firm subs are prepared and manage the building owner's expectations professionally and early.
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
MEP Giants; MEP Annual Report; Mergers and acquisitions; Passive, active fire protection; LED retrofits; HVAC energy efficiency
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me