New construction: Cleveland Clinic Pathology and Laboratory Medicine Institute; Karpinski Engineering

Source: Karpinski Engineering

08/09/2012


Laboratory gas systems (Click to enlarge)Project name: Cleveland Clinic Pathology and Laboratory Medicine Institute

Location: Cleveland, Ohio

Firm name: Karpinski Engineering

Project type, building type: New construction, research/lab/high-tech

Project duration: 1.2 years

Project completion date: Jan. 20, 2012

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $35 million

Engineering challenges

The challenges associated with the project complexity and time schedule were met by utilizing BIM. The contractors were provided with a complete 3-D model of the building including all MEP Air handling unit (100% outside air) (Click to enlarge)architectural and structural systems. Through biweekly BIM team coordination meetings with the contractors, architects, engineers, and construction managers, conflicts were identified and resolved immediately. The team approach that was deployed during the coordination meetings allowed equipment and systems to be installed with minimal changes in the field. The construction management team stated that without the BIM coordination process, the project would have not been built on time and within budget. A 40% energy savings over ASHRAE 90.1 was critical to obtaining the LEED Gold certification. Energy-saving measures included heat recovery coils, VAV lab hoods, ultrasonic humidification, and LED lighting.

Solutions

To deal with these design constraints, the HVAC design utilized a central water system supplying local water-cooled HVAC units, with air cool units serving the public and food courts. Pump staging and VFDs were used to vary water supply to meet the partial load conditions and provide a more energy-efficient system. In order to deal with the backup power requirements and limited space, the generators were located in the underground areas with exhaust and cooling water systems skillfully routed to the roof level and hidden from view. The supply air is routed underground utilizing a ductwork system powered by a set of in-line fans, and the exhaust air is removed via strategically located air shafts hidden from view and powered by dedicated up-blast fans.

Additional Information 

View a presentation from Karpinski Engineering on the project

Emergency power generator (Click to enlarge)Heat recovery piping mains (Click to enlarge)



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
40 under 40
Integrating lighting, HVAC systems; Use building energy modeling software to balance lighting and HVAC systems
Engineering hospital electrical systems, Boilers and boiler systems, Building envelope best practices
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Preventing arc flash, Backup power fuel choices, power for high-tech facilities
Using BIM in electrical power design; Closed-transition transfer; Medium-voltage distribution; Diesel emission regulations; Increasing emergency power capacity

Poll of the Week

What percentage of your time is spent commissioning building projects?
0% to 25%
26% to 50%
51% to 75%
75% to 100%


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.