Constructed in the late 1920s, Columbus City Hall represents the art deco style that was very prominent throughout that era. While the building still has the original charm and character that it did when it was first built, the HVAC and lighting systems have aged significantly and are in need of an upgrade. The existing HVAC system is a hodgepodge of different systems that have been added and modified over the years.

The existing HVAC equipment will be removed and replaced with a new four-pipe fan coil system supplemented with dedicated outdoor air units (DOAU) to provide proper ventilation. The four-pipe fan coil system can prove to be 10% to 15% more efficient than a traditional variable air volume (VAV) system because the need for reheat has been eliminated and the DOAU can provide the minimum amount of outdoor air required. With a traditional VAV system, there is a tendency to over-ventilate a space because of the need to calculate outdoor air requirements based on the critical space method.

The majority of existing lighting at city hall consists of T12 fluorescent and incandescent lamps in a variety of fixture types that appear very dated. There are several historic pendants in many of the main hallways that use screw-in incandescent candelabras. Many of these historic luminaires have been retrofitted with replacement screw-in fluorescents, which have taken away from the historic look. These fixtures are being removed, shipped to a custom luminaire manufacturer, refurbished and cleaned, and then fit-out with LED light sources consistent to the original incandescent look. This will reduce the luminaires’ energy consumption by nearly 80% from their original incandescent versions and by more than 30% of their retrofit compact fluorescents.

The T12 parabolic and lensed troffers will be replaced with T5 volumetric type luminaires and T8 lensed troffers in the majority of spaces. It is anticipated that the new luminaires will be able to produce the same light levels that currently exist while reducing consumption by up to 30%. Changing from T12 to T5 luminaires will result in approximately a $1/sq-ft savings annually. There is more than 90,000 sq-ft of space being renovated at city hall, resulting in a $90,000 savings. This number does not take into account additional savings that will be witnessed by occupancy sensor and time of day control automatic lighting control.

A major culprit of energy consumption at city hall is the exterior floor lights, 400 and 1000 W metal halide drum-style flood lights that consume 460 and 1080 W, respectively. The total exterior consumption is 36,960 W. These are being replaced by LED wall washers and flood lights that consume a mere 30 W each. The total wattage of the new LED system that is capable of producing any color in the spectrum as called for by the city of Columbus for special events is 4160 W. This is a reduction of 89% and can yield a payback of less than seven years, even with the significant investment for color-changing LEDs upfront. It currently costs the city approximately $26/night to run the metal halides; this number will be reduced to $3/night, based on an 8-hour night at $0.09 per kWh.

With these lighting and HVAC changes, the city hall renovation is in the process of pursuing U.S. Green Building Council LEED Certification.

 


Return to:

Integrating Lighting and HVAC Retrofits: Main Story

Integrating Lighting and HVAC Retrofits: Complex Office Building Retrofit (Case Study)

 

 



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.