Casino selects backup power system

A 4-MW standby power system backs up life safety equipment, gaming, and security loads for an entertainment venue in the Arizona desert.

10/27/2014


Figure 4: The $230 million Twin Arrows resort and casino includes 12 table games and 4 poker tables. Photo courtesy of Twin Arrows Navajo Casino ResoThe Twin Arrows Navajo Casino Resort is a destination resort in a rural location about 25 miles east of Flagstaff, Ariz. As a flagship property of the Navajo Nation Gaming Enterprise (NNGE), the 267,000-sq-ft gambling and hospitality venue includes more than 1,000 slot machines, a conference center, indoor pool, restaurants, and a 200-room hotel. To protect the facility from utility power outages caused by the area’s frequent thunderstorms and high winds, NNGE selected an advanced 4-MW standby power system from Cummins Power Generation.

“Reliable backup power is critical for us as a gaming facility,” said Jim Wanamaker, facilities manager for NNGE. “For us, life safety is always of the utmost importance. Beyond that, the critical requirement for us as a gaming operation is that we don’t lose power to the gaming floor or the gaming slot systems to maintain play on the floor. Security systems are also crucial: if security were to go down, we’d have to shut down the gaming systems as well.”

The resort was designed by the Friedmutter Group architects of Las Vegas in collaboration with the Navajo tribal members and JBA Consulting Engineers. To ensure power is available at all times, Twin Arrows has several redundant systems that include dual utility feeds, multiple uninterruptible power supply (UPS) systems, and a pair of standby diesel generators in a 2N configuration. 

Figure 2: The enclosure and tank packages on the generators were manufactured at the Cummins Rocky Mountain production facility in Henderson, Colo.The two standby generators operate at 480 V and produce 2 MW each. With a current total facility load of about 1.25 MW, one generator is sufficient to supply the total load in the event of an outage. The second or redundant generator provides several advantages: it is a backup to the first generator, it allows maintenance to be performed without jeopardizing system reliability, and, in an extended outage, it can take over if the first generator consumes its 24-hour supply of fuel.

The generators also operate in parallel and share load using the Cummins PowerCommand digital generator controls and parallel with the utility grid using the PowerCommand digital master control (DMC 300). When an outage occurs, both generators start and assume load. However, the digital master control will shut down the redundant generator when the facility load drops below 80% of a single unit, saving fuel and engine wear. Each generator is housed in a sound-attenuated enclosure, located outdoors.

The casino’s first line of defense is the facility’s three UPS backup units. The battery-powered units maintain power to key casino operations that include emergency lighting, security and surveillance, gaming floor and player management systems, HVAC, and other systems. The UPS systems bridge the approximate 10-second gap between when normal power goes out and the load is assumed by the diesel generators.

 

Soft-loading, closed-transition design eliminates disruptions

Figure 1: The DMC 300 paralleling system, consisting of a DMC 300 digital master control, nine sections of switchgear, and two sections of low-voltage controls, employs an icon-based touchscreen interface, simplifying operation and diagnostics. All graphics courtesy: Cummins Power Generation

“The standby power system is set up as a prioritized system so that the emergency systems, such as the fire pump, fire alarm, and smoke control systems get the highest priority,” said Leslie Fernandez, senior electrical engineer with Las Vegas-based JBA Consulting Engineers. “The second priority is the legally required standby systems, such as emergency lighting and elevators, followed by business-critical equipment that includes security systems and the gaming floor. The soft-loading, closed-transition design allows the generator sets to assume the load or transfer the load back to the utility in a smooth, controlled way so that voltage and frequency transients (sags) are avoided. 

The configuration of the Cummins DMC 300 paralleling system was selected after another manufacturer’s system was ruled out as too costly. “With the simpler Cummins design, it became easier to isolate one or two sections of the common bus without the danger of an adjacent bus becoming energized,” said Chris Tornillo, power systems manager with Cummins Rocky Mountain. “This will allow work to be performed on the de-energized bus with the appropriate minimum personal protection equipment.” 

Figure 3: The Cummins low-voltage generators provide a total of 4 MW of standby power for the Twin Arrows resort.

Final validation testing with facility loads and a load bank on the generators were completed in early 2013 in preparation for the resort’s May 2013 grand opening. The facility has experienced several utility outages since the standby system was installed and, according to Wanamaker, the system’s performance has been exceptional. This means Twin Arrow guests can enjoy the casino and hotel facilities no matter what the weather—and save their luck for the games.

All major active systems for the Twin Arrows resort were designed using building information modeling (BIM), Fernandez said. Architects created an extremely detailed 3-D computer model of the structure, with engineers from JBA Consulting Engineers and others, such as the lighting designers, adding their systems. Ultimately, the coordinated efficiencies of BIM helped to reduce costs on the project. View a fly-through video tour of the resort’s BIM design.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Commissioning lighting control systems; 2016 Commissioning Giants; Design high-efficiency hot water systems for hospitals; Evaluating condensation and condensate
Solving HVAC challenges; Thermal comfort criteria; Liquid-immersion cooling; Specifying VRF systems; 2016 Product of the Year winners
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
Designing generator systems; Using online commissioning tools; Selective coordination best practices
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me