TAB for bed tower is being finished. Hospital level 3 punch list is in progress.


June 2015 update:

  • Finishing out TAB for the bed tower (HL4-7)
  • Hospital level 3 punch list is ongoing
  • BSL3 PVTs are underway
  • Continuing IBS punch list and turnover.

 Generator room duct work addition. Courtesy: Kristi Koenig

 NICU patient room. Courtesy: Kristi Koenig

Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Sizing water pipes, ASHRAE 90.1, recovering waste heat, and more
Sizing water pipes, ASHRAE 90.1, recovering waste heat, and more
Developing lighting solutions; Designing lighting systems; Integrating fire alarm and HVAC systems
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me