Standby Systems for Hospital Campuses and Data Centers

October 21, 2010

 

Exam for Continuing Education Units

 

1.0  learning units (0.1  CEUs)

 

You must get 8 of 10 questions correct to pass the exam. You may retake the exam if necessary. You will be notified whether you passed or failed automatically after taking the exam. Upon passing the exam, a hardcopy certificate will be mailed within 30 days to you at the address you provide below.

 

 

1.Name *
2.Street Address *
3.Street Address 2 *
4.City *
5.State *
6.Zip Code *
7.Email address *
8.Telephone Number *
9.AIA Registration Number
10.Question 1 *

According to speaker Tom Divine, protecting a hospital against flooding includes

Elevate critical systems
Add loads to emergency system
Install flood barriers
Isolate vulnerable spaces
All of the above
11.Question 2 *

According to speaker Tom Divine, the rebuilt facility underwent a shutdown test

True
False
12.Question 3 *

According to speaker Tom Divine, the glitches encountered in the rebuilt facility did NOT include:

Revised feeder construction strategy
Transitional state
UPS battery bank wired backward
Outage durations
ATS phase rotation
13.Question 4 *

According to speaker Tom Divine, none of the motor control centers had to be replaced

True
False
14.Question 5 *

According to speaker Tom Divine, the Lessons Learned included:

Early definition of existing conditions
Electricians assist in field investigation
Examine transitional states
All of the above
None of the above
15.Question 6 *

According to speaker Scott Kesler, when designing a spec data center, the standby system requirements for the maximum expected power loads are usually well defined.

True
False
16.Question 7 *

According to speaker Scott Kesler, when considering the emergency power system, the electrical utility parameters are not relevant to the design.

True
False
17.Question 8 *

According to speaker Scott Kesler, a standby power system for data centers consists only of generators and transfer switches.

True
False
18.Question 9 *

According to speaker Scott Kesler, the electrical system voltage will impact the type of equipment used and the space required.

True
False
19.Question 10 *

According to speaker Scott Kesler, reliability, redundancy and maintenance considerations should be taken into account when designing an emergency power system.

True
False