March 4 Southland Industries update: Roughing in systems, ceilings and diffusers complete, parking garages underway, beginning to prepare to start chilled water plant

Roughing in systems on levels 2, 4, 5, and 6; ceilings and diffusers are complete or near completion; all 3 parking garages are underway; preparation to started the chilled water plant is underway.

03/07/2014


As of March 4, 2014:

  • Southland Industries is currently roughing in systems on levels 2, 4, 5, & 6 in the hospital. Basement, levels 1, 2, 3, 4, and 5 drywall walls are underway.
  • The West Clinic has ceilings & diffusers are complete, the North Clinic has diffusers going into the ceilings, the South Clinic has drywall being installed on levels 1, 2, and 3.
  • All 3 parking garages are underway.
  • Southland Industries is beginning to prepare to start the chilled water plant, the refrigerant will be charged into the chillers in the coming weeks.

                         CUP Steam to heating hot water heat exchangers. All photos courtesy of Gary LovewellHospital atrium.