Using BAS for M&V

03/26/2014


M&V codes and standards

For new construction projects, a number of codes and standards are emerging to drive the process. One of the most common guides driving an M&V process is LEED, which includes general requirements for trend analysis to verify performance as a part of the Energy and Atmosphere credit. Under EA Credit 5 for new construction projects, LEED offers a credit for developing and implementing a full-fledged M&V plan.

In addition to LEED, building codes in a number of jurisdictions are beginning to adopt Cx requirements that include M&V elements. The Seattle and Washington State Energy Codes are examples, in addition to Title 24 in California. In fact, the latest edition of Title 24, which will be effective in mid-2014, will drive new construction Cx processes toward requirements that are very similar to the requirements for LEED fundamental and enhanced Cx.

In contrast, M&V in existing building Cx processes tends to be driven either by the owner or the requirements of a utility incentive program that is funding the project, as mentioned previously. For example, the University of California/California State University/Investor Owned Utility (UC/CSU/IOU) MBCx program generally requires two different forms of M&V:

  1. For the initial RCx phase, energy savings incentives are based on the difference between a whole building meter consumption baseline, which is established prior to implementation, and the baseline that exists at the whole building meter after implementation.
  2. For energy conservation measures implemented subsequent to the initial RCx effort, the savings are incented based on engineering calculations. However, the validity of the calculation is frequently verified using M&V strategies, either at the whole building level or at the system level.

Regardless of the Cx process, most M&V standards and code requirements trace their roots to the International Performance Measurement and Verification Protocol (IPMVP). This standard sets rigorous requirements regarding the protocols, methodology, and tools used to quantify resource savings. In general, and with regard to M&V methodologies, IPMVP suggests four options for determining savings, including retrofit isolation by measuring certain key parameters, retrofit isolation by measuring all parameters, whole facility energy measurement, and calibrated simulation.

M&V plans

During a RCx project, depending on owner project requirements (OPR), input from the operation and maintenance (O&M) team during interviews, and the RCx agent site visits and reviews, a set of goals will be introduced as part of an M&V plan draft. This draft will be reviewed by the owner’s team and finalized. This document will define the extent of M&V. In general, a RCx M&V plan includes the following:

  • The timing to put the RCx contract in place
  • Potential preparations prior to each site visit
  • Site visit timing and requirements
  • Identification of systems (should be included in the RCx project and are part of the M&V plan)
  • Assessment of BAS and control points for each system to identify control points that should be trended
  • Identification of tools (direct and/or indirect monitoring) for launching the trending process
  • Data analysis schedule
  • Development of energy and water saving measures and O&M opportunities
  • Quantification of energy and water saving measures
  • Writing a draft report, owner’s review, final report issuance, and presentation.


No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.