Trane converts unitary products from R-22 to R-410A ahead of schedule

In a three-year global effort to beat federal regulatory due date of Jan. 1, 2010, Trane reengineered products and production plants to phase out R-22 from all unitary products and some chillers. Along the way, Trane introduced 17 new products over 18 months leading up to the completion of the refrigerant conversion project.

By Michael Ivanovich, Editor-in-Chief, CSE

10/28/2009


 

On Oct. 14, 2009, Trane, a business of Ingersoll Rand, completed a global conversion effort from HCFC R-22 to the non-ozone-depleting HFC refrigerant, R-410A, for its entire unitary product line in the Americas to ensure full compliance with federal U.S. Clean Air Act provisions implementing the Montreal Protocol's phase out of HCFCs. Unitary products are packaged products that are designed, built, and tested in manufacturing facilities, then delivered to the customer for quick installation and operation. The Clean Air Act has mandated that no new R-22 products can be shipped after Dec. 31, 2009.

Trane made the announcement at a celebration and Town Hall meeting at the company's plant in Clarkesville, Tenn. ( Click here for videos created by Trane from the event ). At a press briefing held before the Town Hall meeting, Jeff Moe, Director-Global Regulatory Planning & Conformance, Ingersoll Rand, said that Trane was faced with "the most significant regulatory impact the HVAC industry has faced. In the U.S., total conversion away from R-22 use in new equipment must occur by Jan. 1, 2010. At the same time, [mandatory] increased minimum efficiency requirements for commercial unitary are driving additional product change."

Rather than work on the converging refrigerant and efficiency requirements in series, Trane addressed both of them in parallel by redesigning and reengineering all commercial unitary products and some chiller products over a three year period. In the end, marked by the celebration and press event at the Clarkesville plant, not only are these products using non-ozone-depleting refrigerants, they are said to have improved efficiency, reliability, serviceability, manufacturability and safety.

During a tour of the Clarksville manufacturing plant, Larry Griffith, Trane Manufacturing Engineering Leader said, "U.S. commercial factories are no longer taking orders to produce R-22 equipment. Last U.S. production of commercial R-22 units will occur in December." For a video of the Clarksville plant tour, click here .

The following statistics underscore the size and significance of Trane's achievement:
• $100 million invested in new manufacturing systems and equipment in our facilities to manufacture these new products in the Americas.
• More than $11 million in research, testing and development costs.
• More than 500 employees from the U.S., China, and France worked more than 3 million man-hours on the design and engineering side alone.
• Project completed on time.

As part of this reengineering and redesign effort, Commercial Systems launched 17 new products over the past 18 months. According to Trane, this is more new products in a year and a half than all of the new products that the company has introduced over the past 20 years. The new products were the result of direct customer feedback requesting more comfort-system options to navigate the current economic environment as well as Read about the key product highlights from the recently revealed products at the following links:

Model CGAM air-cooled scroll chiller :

Odyssey split-system

Precedent rooftop units

Tracer SC system

Performance Climate Changer air handler

 

 



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Integrating lighting, HVAC systems, Energy codes and lighting, BIM and fire protection engineering
Engineering hospital electrical systems, Boilers and boiler systems, Building envelope best practices
Hospital indoor air quality, ASHRAE 90.1 update, Specifying piping materials, Integrated project delivery
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Estimating data center PUE, Design tips for cost savings, Networked controls, NFPA 70E
Preventing arc flash, Backup power fuel choices, power for high-tech facilities
Using BIM in electrical power design; Closed-transition transfer; Medium-voltage distribution; Diesel emission regulations; Increasing emergency power capacity
About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.