CSE: What are some of the tools and systems you rely on to commission projects? 

Feyler: In addition to the obvious ladders for above-ceiling observation, heat guns, digital thermometers, light and sound meters, stop watch, and laser pointers are used during the testing phase. During testing of sophisticated systems, our firm will have verbiage in the commissioning specifications that the contractor is to provide a third-party certified testing agency for infrared scanning, power quality metering, and NETA electrical testing. RDK will also carry a third-party test-and-balance (TAB) contractor for the spot checking of the testing and balancing report, and in some cases the owner has RDK carry the TAB contractor under the commissioning services contract to facilitate the TAB contractor for the entire project. This scenario is beneficial to the owner and the CxA. 

Szel: Some key tools are infrared temperature scanners, data loggers, and power quality monitors. It is important for there to be skilled technicians who can interpret the results. Also, patience is important for those days when the plan just doesn’t go as expected.

Wolff: It’s pretty typical for our commissioning engineers to use a digital multi-meter, noncontact thermometer, digital thermometer with insertion probes and thermocouples, IAQ meter, digital manometer, thermal imager, data loggers, laptop/tablet, and digital cameras. 

York: Every CxA’s toolbox should contain a wide range of physical items: flow hood, pressure gauges (water and air), thermometers, hygrometers, data loggers, anemometer, voltmeter, ammeter, ground fault interruption (GFI) tester, screwdrivers, rulers, and camera; but more importantly should include proven process tools to collect and organize the enormous amount of data collected on a commissioning project. The CxA should also be able to rely on ASHRAE, NETA, NFPA, and AABC guidelines to help evaluate system performance. 



Gerry , Ontario, Canada, 08/29/13 06:33 AM:

Excellent comments we could not agree more
J.R. , TN, United States, 09/04/13 04:27 PM:

Good comments from some large users of the commissioning process.
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Integrating electrical and HVAC for energy efficiency; Mixed-use buildings; ASHRAE 90.4; Wireless fire alarms assessment and challenges
integrated building networks, NFPA 99, recover waste heat, chilled water systems, Internet of Things, BAS controls
40 Under 40; Performance-based design; Clean agent fire suppression; NFPA 92; Future of commissioning; Successful project management principles
Transformers; Electrical system design; Selecting and sizing transformers; Grounded and ungrounded system design, Paralleling generator systems
Commissioning electrical systems; Designing emergency and standby generator systems; VFDs in high-performance buildings
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
This course focuses on climate analysis, appropriateness of cooling system selection, and combining cooling systems.
This course will help identify and reveal electrical hazards and identify the solutions to implementing and maintaining a safe work environment.
This course explains how maintaining power and communication systems through emergency power-generation systems is critical.
click me