Tips and tricks for commissioning, balancing buildings

08/28/2013



CSE: ASHRAE Standard 202P, Commissioning Process for Buildings and Systems, identifies the minimum acceptable commissioning process for buildings and systems as described in ASHRAE’s Guideline 0-2005, The Commissioning Process. How have you applied this standard in a recent project, and what challenges did you overcome? 

Bauers: We are a NEBB-certified firm. As a member of the NEBB BSC Committee, we developed our procedural standards to comply with the ASHRAE guidelines on commissioning. Given that we have taken this approach, we apply the NEBB standard to commissioning. The challenge in the marketplace that we are finding is that our process and the NEBB standard seem to be more rigorous than many of the processes implemented by our competitors. Using a hands-on approach to commissioning, we are substantially more involved—particularly during construction—than many other firms against whom we price our services. 

Szel: Most of our commissioning projects are either for LEED certification or for critical facilities, which have their own specific requirements for commissioning that exceed the ASHRAE standard. With our critical facilities clients, we try to get engaged early in the process so we have input in the commissioning specifications for the vendors and contractors; we often write them entirely. 

Wolff: We have not applied 202P specifically to a project, though the principles contained within it align with our standard delivery. Another way to look at this is that McKinstry Commissioning has, in effect, already been providing 202P services, since our delivery method is already in accordance with this standard. 

York: I personally have not used the ASHRAE Standard 202P for a commissioning project. The standard was recently released by ASHRAE and most owners and CxAs are still learning the standard. The 202P standard does a great job specifying the minimum commissioning services required to ensure the owner extracts the most value from commissioning. The standard is very similar to the USGBC’s BD&C LEED EA Pre-requisite 1 requirements with the addition of submittal review, systems manual, and training, which we have applied on multiple projects. For systems manuals to be of long-term value, you need an engaged owner in the process—a owner that understands how the systems manual can support long-term operations and maintenance as well as potential system limitations as churn occurs.


<< First < Previous 1 2 3 4 5 6 7 Next > Last >>

Gerry , Ontario, Canada, 08/29/13 06:33 AM:

Excellent comments we could not agree more
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
Cannon Design’s blog is a place for the many voices of the firm to share thoughts and news related to current projects...
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.