Sangre de Cristo

New construction: Sangre de Cristo; M.E. GROUP

08/09/2012


The exterior of the school faces west, resulting in maximum use of sunlight. Courtesy: James H. Berchert Photography, via klipp Architecture (Click to enlarge)Project name: Sangre de Cristo

Location: Mosca, Colo.

Firm name: M.E. GROUP

Project type, building type: New construction, school (K-12)

Project duration: 3 years

Project completion date: Feb. 29, 2012

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $7.2 million

Engineering challenges

The design team considered many challenges as we kicked off this project—not least that class sessions occur in this facility during the The west side exterior from the back of the building is shown. Courtesy: James H. Berchert Photography, via klipp Architecture (Click to enlarge)harshest time of the year. As this climate region (6B) is a heating-dominated climate, we knew we needed a well-insulated building and could introduce passive solar strategies, but also knew we would need some form of heating in the building. With a climate similar to that found in Calgary, Alberta (over 1,000 miles north), heating became the primary challenge on this project. With the strong presence of true geothermal resources in this region, we spent considerable time exploring this option.

The team approached design thinking that if we could tap into the essentially free hot water source underground and use a direct-use geothermal system, then the only energy we would have to expend to heat the building would be the pump power, resulting in an extremely low energy use for the building. After discussions with the Department of Energy, we found the cost of extracting and then reinjecting the This image shows the installation of the geo-exchange well field. Courtesy: M.E. Group (Click to enlarge)water back down 3,000 to 5,000 ft below the surface just wasn’t feasible for a project of this size. Our strategy would have made sense for a much larger application with a faster return on investment. Somewhat stumped, we started looking at what utility options were available. With Sangre De Cristo being in such a rural location, there was no natural gas supply in the area. Buildings rely on either propane or electricity to heat their space. The school district has experienced extremely high propane costs over the years, and they continue to escalate rapidly. It was clear that propane wasn’t a very responsible long-term choice as the primary heating system.

Solutions 

We needed another solution. After ruling out these two options, we steered toward an electric solution to the heating problem. Despite getting a few curve balls thrown at us with the true geothermal system, we did find another resource in the region, which was the soil itself. Because of the runoff from the mountains surrounding this valley, there is a really high water table and a nearly constant churn of Large windows encourage natural daylight within the space. Courtesy: James H. Berchert Photography, via klipp Architecture (Click to enlarge)Water-to-water heat pumps are positioned throughout the building. Courtesy: M.E. Group (Click to enlarge)water just a few feet below the surface. Our engineering minds went to work, and as engineers know, water is a great heat transfer medium. So, we connected the use of the really good thermal conductivity in the soil with the use of a horizontal geothermal system. Going horizontal instead of vertical saved about $250,000 on the project and provides excellent performance with the high water table. Located about 12 ft below the surface, we coupled the geothermal system with water heat pumps to generate hot water for the building and then simply pipe the hot water to perimeter baseboard heating elements located throughout the building. There was our heating solution.

The cooling requirements for the building are so minimal that we had the opportunity to combine the cooling system with the ventilation system. We supplied outside air in most of the spaces with displacement ventilation and keep that temperature at about 65 to 68 F. After performing an analysis, we found that the amount of air required to cool a space rarely exceeds the amount of air required to ventilate a space. So that same system allowed us to do both and respond to a detection of high carbon dioxide or call for space cooling. We positioned a few water-to-air heat pumps sprinkled throughout the building for some of the higher-load spaces, but primarily our cooling is accomplished with evaporative cooling and an energy recovery ventilator, ducted to the space with displacement ventilation. Project successes include: 51% energy cost savings above ASHRAE 90.1 2007, 80% projected energy cost savings for the district, and projected energy use of 22.1 kBtu/SF/yr (four times better than average for Colorado schools).

Additional information

For more project details, view a presentation by the M.E. GROUP on the Sangre de Cristo.

View a video from the M.E. Group on the challenges posed by the Sangre de Cristo.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
2014 Product of the Year finalists: Vote now; Boiler systems; Indirect cooling; Integrating lighting, HVAC
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.