Reducing electrical system costs

03/04/2013


Use the load as an advantage

For derating conductors in underground installations and for voltage drop, derate based on actual load instead of circuit-breaker rating. The NEC recommends that conductors be derated for underground installations and voltage drop. However, if the required voltage is not available at the load, the load will fail to operate properly. 

The most conservative approach is to use the circuit breaker ampacity to determine the load size for derating calculations. However, this can cause the conductors to be significantly oversized, especially when the conductors are servicing a dedicated load. For dedicated loads, use the actual maximum current-based nameplate rating of the device or the manufacturer’s data sheet as the load size for derating calculations. This results in smaller, less expensive conductors to install. In no case shall derated conductor sizes be less than nonderated conductors for the same device, but in some instances the conductor size may not need to be increased. For panels, switchboards, or similar types of equipment, it is recommended to base derating calculations on the equipment’s full-load capacity because the loads may change over time due to facility retrofits or upgrades. 

When underground is not an option

Figure 2: Cable tray can be used instead of conduit in situations that prevent underground feeder installation, especially if many conductors must be routed. Courtesy: CH2M HillIn cases where feeders can’t be installed underground, consider using cable tray instead of conduit (see Figure 2). While the cost and installation of cable tray is greater than that of conduit, overall cost-savings can be achieved if there is a need to route a significant quantity of conductors. The cost break point will vary depending on the facility type, width, and material of the tray itself along with the quantity of feeders being installed. This cost break point should also incorporate the difference in labor hours to pull the conductors through the conduit versus the reduced hours for laying conductors in the tray. An added benefit is that cable tray easily allows future flexibility in adding, changing, or removing conductors if the loads change. 

Another option is to use busway for the large feeders between switchgear, switchboards, and panelboards. This can be a cost-effective solution compared to using conduit and cable for a large installation. 

Battery packs

For facilities that need emergency power for life safety only (i.e., emergency lighting and fire alarm panels), consider using battery-backed devices rather than an emergency generator. Emergency generation systems are expensive to purchase, install, operate, and maintain. Even if the design is already using a standby or backup generator for other loads, battery-backed life-safety equipment can still be a cost-effective solution. 

The NEC requires that where generators are supplying any combination of life safety (emergency), standby, and backup loads, they must have the capability of selective load pickup and load shedding to prioritize the loads and ensure adequate power for the life safety loads. Boxes, enclosures, transfer switches, and panels must be permanently marked to identify these devices as part of the emergency system. The NEC further requires that wiring from an emergency source or panel to the load be independent from all other wiring and equipment. Material costs for a generator load management system, permanent identification of all systems, and independent emergency wiring—in addition to the labor to install these systems—can exceed the costs of a life-safety system designed using battery-backed devices.

Offsite prefabrication

Specify and design equipment, components, and assemblies such that they can be prefabricated offsite. Prefabrication is a technique that divides complex electrical installations into manageable subassemblies. These subassemblies can be designed and constructed at offsite manufacturing facilities. Advantages to this approach include reduced on-site labor costs, improved quality control, and improved schedule performance. Often, prefabrication will occur concurrently with on-site preparation, thereby improving the speed of construction for the entire project and potentially reducing the impact of critical-path items. 

Prefabricated components undergo quality control procedures and functional testing, and can be partially commissioned prior to shipment to the site. Prefabrication also allows an increased level of material utilization controls, which reduces material waste, improves overall sustainability of the installation, and reduces the environmental impact of construction. Additional advantages of prefabricated assemblies include enhanced worker safety, minimized delays due to weather or labor shortages, and improved site security. 



TOM , TX, United States, 03/06/13 09:06 AM:

Some utilities require a 4 wire incoming service even when there are only 3 wire motor loads.
PRASAD , GA, United States, 03/06/13 10:25 AM:

Interesting article !
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.