Port of Long Beach, Middle Harbor Redevelopment

System overhaul: Port of Long Beach, Middle Harbor Redevelopment; P2S Engineering

08/09/2012


Port of Long Beach aerial viewProject name: Port of Long Beach, Middle Harbor Redevelopment

Location: Long Beach, Calif.

Firm name: P2S Engineering

Project type, building type: System overhaul, manufacturing

Project duration: 6 years

Project completion date: June 9, 2012

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $70 million

Engineering challenges

The Port’s middle harbor container shipping terminals were old, outdated, and designed for a past era of containerized shipping. To improve efficiency and meet current 21st century environmental standards, they had to be updated. This would allow the Port of Long Beach not only the opportunity to utilize new technologies, but also infrastructure upgrades that would improve the environment. As a result, once completed, the power infrastructure will have the capacity to fully support not only typical terminal needs (medium-voltage quay cranes, site lighting, and building distribution), but also greener port technologies such as shore-to-ship power and electrified rail-mounted gantry cranes in the container yard.

Solutions

P2S designed a reliable distribution system to serve present and future needs for the Middle Harbor. The completed mega-terminal will be served by a 112 MVA, 66-12 kV substation that will be constructed in stages over the next 10 years. The terminal also includes a 12 kV intermodal yard substation; (3) 6.6 kV shore power substations; (10) 480 V reefer substations; site distribution to facilitate power and communications to medium-voltage quay and stacker cranes, shore power outlets, reefer outlets, terminal site lighting, and buildings; and a state-of-the-art energy and power management solution for managing the increased demands of the electrified terminal. P2S is also advancing and standardizing shore-to-ship power solutions by leading the development of an international IEC/ISO/IEEE standard for shore-to-ship power. This ensures that the shore-to-ship power system at the Middle Harbor is state-of-the-art. It will also serve as an example for other terminals nationwide to follow.

Artist rendering of Port of Long BeachArtist rendering of Port of Long Beach



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
Cannon Design’s blog is a place for the many voices of the firm to share thoughts and news related to current projects...
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.