November 1 Southland Industries update: Roughing-in Levels 2 and 5; temporary air conditioning; parking garages

Roughing-in systems on Levels 2 and 5; North and West Clinics being prepared for temporary air conditioning; CUP stream plant being finalized; three parking garages underway.

By Gary Lovewell, LEED AP BD+C November 15, 2013

As of Nov. 1, 2013:

  • Currently roughing in systems on Levels 2 and 5 in the hospital.
  • The North and West Clinics are being prepared for temporary air conditioning with the house air handling units. The South Clinic rough-in is underway on Level 1 with all levels of structure and interstitial floors complete.
  • The CUP stream plant is being finalized with the majority of the heat exchangers and specialty equipment bring set and connected over the next couple of months.
  • All three parking garages are underway.