Motorola Mobility

Office; Motorola Mobility; Alfa Tech

08/15/2013


This photo shows the interior of building. Courtesy: Alfa TechEngineering firm: Alfa Tech
2013 MEP Giants rank:
63
Project:
Motorola Mobility
Address:
Sunnyvale, Calif., United States
Building type:
Office
Project type:
Other
Engineering services:
Electrical/Power, HVAC
Project timeline:
March 2011 to March 2012
Engineering services budget:
$10.59 million
MEP budget:
$11.72 million

Challenges

The engineering challenges for this multiple-floor (1st, 6th, 7th, and 8th floors; 35,000 sq ft each floor) tenant improvement on a cold shell high-rise building project included the fast track schedule, cost, life safety smoke control redesign due to new 2-hour separation walls required by the city of Sunnyvale, and food service makeup air.

Solutions

For scheduling and cost, the solution was to proceed with an integrated design approach which forces all parties, including engineers and subcontractors, to work together on a hands-on approach to speed up the shop drawing process, responses to requests for information, and field issues. For smoke control, the solution was to hire an expeditor that had worked with the city before to speed up the approval process. For the food service, instead of bringing makeup air from the exterior envelope (not preferred in a high-profile, high-rise building) and conditioning it, the engineer and CMI (the HVAC subcontractor) worked together on a design-assist basis and provided the innovative design, which used the building return air for the kitchen hood makeup air, saving energy and reducing cost.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
40 Under 40; Stand-alone medical buildings; NFPA 92; Specialty fire suppression; Applying 90.1 in lighting design
2016 Product of the Year Finalists: Vote now; Data center Q&A; LED codes; Smart buildings
Fire pump power system design: How to design safe, reliable fire pump power service; Water management in commercial buildings; Emergency egress, illumination
Designing generator systems; Using online commissioning tools; Selective coordination best practices
Understanding transfer switch operation; Coordinating protective devices; Analyzing NEC 2014 changes; Cooling data centers
Designing positive-energy buildings; Ensuring power quality; Complying with NFPA 110; Minimizing arc flash hazards
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
click me