Energy modeling for LEED submission was done on a recent project in which natural ventilation and a radiant floor cooling system were proposed for the dining area of a food court in a local university in Southern California.

09/24/2012


The EQuest systems configuration screen does not represent true system configuration. Courtesy: EQuest, version 3.64Energy modeling for U.S. Green Building Council LEED submission was done on a recent project in which natural ventilation and a radiant floor cooling system were proposed for the dining area of a food court in a local university in Southern California. EQuest was used because it was the most appropriate software at the time, but its developers did not envision such a building, so “workarounds” had to be created to mimic the actual energy use of the building.

Because the design incorporated a mixed-mode approach, and none of the currently available engines allows for multiple systems serving the same space, it was necessary to create the radiant systems as serving “dummy” zones with simulated cooling coils served by fans with 0.0001 kW/cfm energy (because zeroing out fan energy in EQuest can cause instability). Furthermore, it was necessary to perform a dynamic heat transfer analysis in an alternate program to represent a schedule of operation to represent when the natural ventilation was active (in the typical meteorological year file) and when the air conditioning units had to be scheduled to be on for the primary zone.

As shown in Figure 3, there is no way graphically to represent the systems based on the available components in the Schematic Design Wizard. However, with the detailed modules of EQuest and a substantial amount of review of the *.sim files, it was possible to get a reasonably good representation of the energy performance. This was an improvement on the manipulation of baseboard heating modules to simulate radiant floor heating and allowed the computation of cooling energy. While EQuest does have a natural ventilation capability, the complexity of changeover systems for mixed mode approaches did require the heavier manual manipulation of files to represent all of the energy components adequately and meet the expectations of the LEED reviewer panel.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.