H.D. Woodson opening ceremonyProject name: H.D. Woodson High School

Location: Washington, D.C.

Firm name: Setty Group

Project type, building type: New construction, school

Project duration: 3 years

Project completion date: Aug. 17, 2011

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $12 million

Engineering challenges

H.D. Woodson High School holds the distinction of being the first newly constructed Washington, D.C., high school in nearly 40 years. With this merit came the challenge to not only comply with all requirements of the local constituency but also to bring forth a conscious effort in establishing the benchmark for all future Washington, D.C., schools and surpass the minimum requirements of local energy code, ASHRAE, and U.S. Green Building Council LEED. Some of the challenges included a below-grade main mechanical room and conditioning a natatorium and a large state-of-the-art auditorium while maintaining the high efficiency goals for a project targeting a LEED gold certification. Despite its challenges, the project came in on time and under budget, which is an incredible testament to the entire design and construction team given the project’s sheer size and lofty goals.

H.D. Woodson auditoriumSolutions

Pool dehumidification units were used on the project to condition the large open natatorium space. In keeping with the effort to design above the minimum requirements, and therefore reduce the load on the pool water heaters, waste heat off of the coils of the pool dehumidification unites was hydronically transferred over to the pool water via a heat exchanger. The amount of outside air was also exceeded via an airside economizer cycle to condition the space when ambient conditions were conducive to reduce the mechanical refrigeration requirements for the space. High-efficiency chillers and condensing hot water boilers were used to further improve the energy savings. All dedicated outside air units were also specified with integrated energy recovery wheels, and an automated building automation system was installed to serve all of the equipment in the building. In the state-of-the-art auditorium, architectural floating acoustic clouds for sound baffling were suspended, thereby requiring resizing of all ductwork in intricate detail in order to fit and route it through the webbings of the truss system to meet all of the distribution requirements. All of the ductwork and major piping was modeled and checked for clash detection on a computer before any installation in the field, which allowed for a relatively smoother construction process.

H.D. Woodson basketball courtsH.D. Woodson swimming pool

H.D. Woodson Revit image for its MEP systems



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.