Fast-Tracking with 3D CAD

When officials at Wyckoff Inc., a chemical manufacturer with facilities in South Haven, Mich., wanted to expand production capacity by building an additional 18,000-square-foot plant, they challenged the project team to design, build and commission the new facility in nine months. The result was a fast-track project with design and construction efforts running in parallel.

01/01/1970


When officials at Wyckoff Inc., a chemical manufacturer with facilities in South Haven, Mich., wanted to expand production capacity by building an additional 18,000-square-foot plant, they challenged the project team to design, build and commission the new facility in nine months. The result was a fast-track project with design and construction efforts running in parallel.

VECO, headquartered in Anchorage, Alaska, was contracted for the construction and engineering of the new pharmaceutical production plant. The firm's project team attributes its success in meeting a tight schedule, in part, to the accurate development of a three-dimensional (3D) computer model for the plant.

Faced with large quantities of small piping and tight spacing, designers felt that a two-dimensional computer-aided design (CAD) approach would take much longer to generate the section and elevation drawings, with a greater risk of interferences and errors. Instead, it was decided to model the entire plant in 3D and use the 3D model to address spacing issues during the design process, rather than during construction.

The approach enabled sections of the design to be generated and annotated in hours instead of days. At the same time, 3D modeling made it possible to create isometric drawings automatically based on the information contained in the model, thereby achieving a high level of accuracy.

Designers entered data—location, size, specifications—into the 3D model, which was reviewed daily for interferences. Through close coordination, any conflicts were resolved. Design checkers verified all input and confirmed that the design matched the piping and instrument drawings. Finally, the model was reviewed by project team members.

The piping, fitting and valve data were entered directly into the project database; the project piping material specifications were a direct product from this database. Another time-saving feature was the fact that as soon as a section of the model was completed, a bill of materials could be generated simply by querying the database. The bills were generated prior to the formal issuance of drawings.

In the past, when faced with a plant that was very congested, VECO designers used plastic models to review operating and maintenance clearances, interferences, process designs and locations of all components. Now, they use 3D-CAD models to look at the same items in real time.

For more information about CAD software from Rebis, circle 104 on the Reader Service Card on page 73.





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Water use efficiency: Diminishing water quality, escalating costs; Lowering building energy use; Power for fire pumps
Building envelope and integration; Manufacturing industrial Q&A; NFPA 99; Testing fire systems
Labs and research facilities: Q&A with the experts; Water heating systems; Smart building integration; 40 Under 40 winners
Maintaining low data center PUE; Using eco mode in UPS systems; Commissioning electrical and power systems; Exploring dc power distribution alternatives
Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.