Examples of lighting controls cost savings

This case study shows the impact of lighting controls on whole building energy costs.

11/16/2011


As an example of the cost savings that lighting controls can generate, we have performed a case study of two 24-hour facilities and the impact the lighting controls time schedule has on the whole building energy costs. The energy costs included in this case study account for the reduced lighting load and the impacts to the cooling load and heating loads for each building when the lighting is controlled by a time schedule. For both projects the cost savings in energy usage results in a simple payback of less than 4 years for the lighting controls equipment, labor, and start-up/commissioning.

The two 24-hour facilities evaluated in the case study are mixed industrial and office spaces of 300,000-650,000 sq ft. The lighting in the industrial work areas is controlled with a time clock used to switch lights keyed to specific zones by shift schedule. The control equipment allows zones to be reconfigured down to a fixture level, and fixtures are switched on/off with the time clock schedule or by a timed override switch for each zone. The analysis considers only the industrial area lighting controls system, labor, start-up, and commissioning.

Figure 2: The energy savings gained by a fully functioning lighting controls system pays back so quickly that the start-up and commissioning should never be questioned. Courtesy: Primera Engineers Ltd.

Fimek is an award-winning lighting designer at Primera Engineers Ltd. She is Lighting Certified by the NCQLP and is well versed in lighting calculation and rendering software.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
Designing for energy efficiency; Understanding and applying NFPA 101 for mission critical facilities; Integrating commissioning and testing for fire alarm systems; Optimizing unitary pumping solutions
Economics of HVAC systems; NFPA 110-2016; Designing and choosing modular data centers
Combined heat and power; Assessing replacement of electrical systems; Energy codes and lighting; Salary Survey; Fan efficiency
Tying a microgrid to the smart grid; Paralleling generator systems; Previewing NEC 2017 changes
Driving motor efficiency; Preventing Arc Flash in mission critical facilities; Integrating alternative power and existing electrical systems
Putting COPS into context; Designing medium-voltage electrical systems; Planning and designing resilient, efficient data centers; The nine steps of designing generator fuel systems
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.
Automation Engineer; Wood Group
System Integrator; Cross Integrated Systems Group
Fire & Life Safety Engineer; Technip USA Inc.
click me