Designing labs, research buildings

05/28/2013


CSE: What are some common missteps that engineers might make on a laboratory project?

Michael Chow: Cleaning up power should be considered as many laboratory instruments have sensitive power parameters. Consideration should be given also to using uninterruptible power supply (UPS) systems.

Crutchfield: We sometimes run into lab projects where the old 12 air changes per hour (ACH) rules are still being enforced by the environmental health and safety folks at the various institutions. Couple that with the desire for constant volume hoods, which seem to be favored by maintenance staff, and it’s a recipe for an underperforming building. When we discuss this with the owners and suggest alternate compliance and safety methods, they often recognize that there are better ways to accommodate lab airflows, but many owners are still reluctant to change from their institutionally set policies. We aren’t always able to convince them that alternate methods should be used for their projects, but we feel that it is our responsibility to show them the alternatives, and the economics of the alternatives, so that they can be more informed as owners. The goal is to help them ultimately understand their internal policy, and compare that to current state-of-the-art procedures, so that if they want to make policy changes, they have full understanding of the issues involved.

Ramirez: Design for flexibility in control strategies, input/output expandability, and provide for plenty of instrumentation. Laboratory users are constantly changing, particularly in R&D facilities. Specifying the proper control architecture for achieving functional changes a laboratory space may see over the course of its life, specifying proper material for application (metals, gasket seals, temperature and pressure scales, etc.) to achieve functional changes in the laboratory. Of course, this must be balanced with project budget.

Linamen: One common mistake is in thinking that offices, labs, and classrooms/lecture rooms in lab buildings all need to be served from separate HVAC systems. Segregating these spaces on separate systems requires added space for equipment and supply/return/exhaust risers. For a physical sciences building we worked in, there were sophisticated research and teaching labs, as well as classrooms/lecture halls and offices. There is one HVAC system for the entire building, and one main supply air riser, return air riser, and exhaust air riser. Laboratory air is 100% exhausted. What is frequently not recognized is that for most mixed-use lab buildings, the lab air requirement is usually a major part of the total HVAC air requirement for the entire building, usually 70% or more. If multiple HVAC systems are provided, a percentage of the return air from the offices and classroom spaces must be rejected, so that a corresponding percentage of ventilation air can be provided to maintain air quality. However, if one common HVAC system serves all spaces and if the lab air requirement is a high percentage of the total air requirement, 100% of the air from the offices and classroom spaces can be returned. This reduces the total air requirement for the building. This usually results in fewer air handling units for the building, so it saves first cost, it improves overall flexibility because labs can be converted to non-lab functions and vice versa without major changes to the HVAC, and the non-lab spaces have excellent air quality because they receive higher than normal percentage outside air. This usually makes it more convenient to provide redundancy, because redundancy is only required for the one system. 

CSE: When working in labs outside the United States, what differences, challenges, or best practices have you observed?

Crutchfield: Our experience has confirmed that laboratory standards outside the U.S. have not evolved to the extent they have in the U.S. Standards outside of the U.S. have remained unchanged largely because the international markets have not developed as many new state-of-the-art lab facilities as we have in the U.S. Many of the criteria points such as load densities, air change rates, and fume hood face velocities have not been challenged because the need simply has not occurred. However, with the globalization of industry groups, this is beginning to change. In the European market, attention to overall health and safety within the lab environment requires focused risk assessment by the project team. The project team routinely consists of owners, design professionals, lab operators, and maintenance staff. We have found this refreshing, as clients now understand the critical role appropriate operating procedures serve for laboratory health and safety.

Ramirez: In the United States, it is general practice to assign about 25% of a fee to construction administration. This is generally in the standard design/bid/build project delivery model. Delivery of a similar project abroad is generally a design/assist or design/build delivery model. This will require significantly more on-site support, and commonly we can see the fee structure being more like 55% design and 45% construction administration and/or on-site support, if not an even split. Depending on the project schedule, this is probably the best way for design professionals to manage their risk. 



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
2014 Product of the Year finalists: Vote now; Boiler systems; Indirect cooling; Integrating lighting, HVAC
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.