Cornell University—Stocking Hall Rehabilitation

Addition to existing building: Cornell University—Stocking Hall Rehabilitation; M/E Engineering, P.C.

08/09/2012


The Stocking Hall high-tech food research lab and dairy processing plant are shown.Project name: Cornell University—Stocking Hall Rehabilitation

Location: Ithaca, N.Y.

Firm name: M/E Engineering, P.C.

Project type, building type: Addition to existing building, research/lab/high-tech

Project duration: 7 years

Project completion date: Nov. 30, 2010

Project budget for mechanical, electrical, plumbing, fire protection engineering only: $25.6 million

Engineering challenges

Working in a campus environment where adjacent structures need to remain operational and be connected to the new building while construction takes place. This poses special challenges from a utility standpoint as well as a LEED standpoint.

Solutions

To meet the U.S. Green Building Council LEED requirements as well as Cornell's energy targets, a very aggressive approach to energy efficiency was taken. A number of strategies were incorporated, which included heat recovery on all the air systems, heat recovery on the water cooled condensing units to aid in the heating of outside air for laboratories, an aggressive demand control ventilation strategy that was utilized in the lab spaces, as well as utilizing relief air to assist with the ventilation of lab spaces and the 250-car parking garage.



No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
2014 Product of the Year finalists: Vote now; Boiler systems; Indirect cooling; Integrating lighting, HVAC
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.