Build Value in Now … or Later?

Our enlightening and spirited discussion of value engineering (VE), also known as value analysis, continues. Its ardent defenders have been its practitioners, while the most vocal detractors have been consulting design engineers. For example, Gregory Josephs, P.E., of Philadelphia, was involved with modifications to sedimentation tanks at a large sewage-treatment plant, and VE was mandated by...

01/01/1970


Our enlightening and spirited discussion of value engineering (VE), also known as value analysis, continues. Its ardent defenders have been its practitioners, while the most vocal detractors have been consulting design engineers.

For example, Gregory Josephs, P.E., of Philadelphia, was involved with modifications to sedimentation tanks at a large sewage-treatment plant, and VE was mandated by federal-aid rules—with drawings and specs all but complete.

"The VE report recommended over 100 changes, most of which were impractical," Josephs recalls. "For instance, the VE team suggested modifying tanks with double-vee bottoms to single-vee, thus requiring only a single chain-and-flights per tank—probably never feasible, certainly not with documents 90 percent complete! Many of the changes would have substituted cheaper equipment. To my knowledge, exactly one was acted on—using plastic weir plates instead of metal."

Josephs was most disappointed with the VE firm's tabulation of the cost savings. "Most values were picked out of thin air… [and] only addressed alleged savings, not the costs required to implement [them]. The executive summary stated the total as though all 100-plus recommendations were feasible and desirable.

"That exposure to value engineering left a bad taste in my mouth," Josephs sums up. "The whole concept of major cost savings through VE would seem to suggest that mere design engineers are incompetent."

Similarly, David D. Adams, P.E., president of AMC Engineers, Anchorage, says third-party VE efforts are little more than cost-cutting that often leads to lower first costs—in exchange for higher operations and maintenance (O&M) costs.

"The systemic problem that provides the false justification for VE boils down to engineering fees," Adams believes. "When fees are being squeezed, the last thing an engineer can offer to add is life-cycle cost analysis," or LCCA.

Adams offers an example of how the "quality principle" can help solve the fee/LCCA dilemma. "Two of our public-sector clients have good access to capital funds, but are often shorted on future O&M budgets. They negotiate additional fees at the beginning of projects for engineers to perform LCCA, and they make decisions based on the long-term view," he explains.

The question is, can this approach work for others?

Adams says yes, but it could take some effort. "As a profession, we must resist fee-cutting pressures and educate clients about the benefits of building quality into designs, with LCCA, at the beginning of the design concept."





No comments
Consulting-Specifying Engineer's Product of the Year (POY) contest is the premier award for new products in the HVAC, fire, electrical, and...
Consulting-Specifying Engineer magazine is dedicated to encouraging and recognizing the most talented young individuals...
The MEP Giants program lists the top mechanical, electrical, plumbing, and fire protection engineering firms in the United States.
High-performance buildings; Building envelope and integration; Electrical, HVAC system integration; Smoke control systems; Using BAS for M&V
Pressure piping systems: Designing with ASME; Lab ventilation; Lighting controls; Reduce energy use with VFDs
Smoke control: Designing for proper ventilation; Smart Grid Standard 201P; Commissioning HVAC systems; Boilers and boiler systems
Case Study Database

Case Study Database

Get more exposure for your case study by uploading it to the Consulting-Specifying Engineer case study database, where end-users can identify relevant solutions and explore what the experts are doing to effectively implement a variety of technology and productivity related projects.

These case studies provide examples of how knowledgeable solution providers have used technology, processes and people to create effective and successful implementations in real-world situations. Case studies can be completed by filling out a simple online form where you can outline the project title, abstract, and full story in 1500 words or less; upload photos, videos and a logo.

Click here to visit the Case Study Database and upload your case study.

Protecting standby generators for mission critical facilities; Selecting energy-efficient transformers; Integrating power monitoring systems; Mitigating harmonics in electrical systems
Commissioning electrical systems in mission critical facilities; Anticipating the Smart Grid; Mitigating arc flash hazards in medium-voltage switchgear; Comparing generator sizing software
Integrating BAS, electrical systems; Electrical system flexibility; Hospital electrical distribution; Electrical system grounding
As brand protection manager for Eaton’s Electrical Sector, Tom Grace oversees counterfeit awareness...
Amara Rozgus is chief editor and content manager of Consulting-Specifier Engineer magazine.
IEEE power industry experts bring their combined experience in the electrical power industry...
Michael Heinsdorf, P.E., LEED AP, CDT is an Engineering Specification Writer at ARCOM MasterSpec.