Project Profile: Maynard Holbrook Jackson Jr. International Terminal


Firm name: Sebesta Blomberg

Project building name and location: Maynard Holbrook Jackson Jr. International Terminal, Atlanta, Ga.

Type of building and type of project: Airport Terminal Building, New Construction

Project completion date and project duration: 2012


Engineering challenges and solutions:
                                

Challenge #1: Since this is a CMR project, one of the biggest challenges at MHJIT has been working with multiple contractors. Several of the HVAC and Electrical specifications were not incorporated into their bid documents.


Solution #1: Our solution to this challenge was adding a no-cost change order to their contract and then creating an FTP site to review and download documents. We would download our commissioning testing scripts and the contractor would be able to review, comment and download back to the FTP site so we could incorporate and begin testing.


Challenge #2: Project schedule is a secondary challenge in the project.


Solution #2: Since this is a CMR project, the schedule never seemed to address every contractor’s time frame, as well as monitor and create a commissioning schedule into the project schedule that would include all testing and re-testing for all the contractors.

 

 


Click Here to View More Project Profiles

Poll of the Week

When engineering systems in military buildings, what’s the most difficult issue you face?
Automation and controls
Codes and standards
Electrical and power
Energy efficiency, sustainability
Fire and life safety
HVAC


Click Here for Poll Archives
Sponsored by:

About Us | Contact Us | Advertise | Subscribe to Magazine | Site Map | Privacy Policy
Home | Channels | New Products | Media Library | Connect | Industry News | Events and Awards | Newsletters | Blogs | Magazine
Control Engineering | Plant Engineering | Consulting-Specifying Engineer
All content copyright © 2010-2013 CFE Media. All rights reserved.