Chicago Hotel's New Cooling Tower Gets a Lift

-- Consulting-Specifying Engineer, 1/1/2005

Chicago's Palmer House Hilton needed to replace its cooling tower and called on industrial and commercial HVAC firm Team Mechanical, Inc. (TMI) to aid with the purchasing and installation of the tower onto the roof of the 24-floor hotel. TMI worked with Maddock Industries to purchase the new $250,000, 112,000-lb. Marley Cooling Technologies cooling tower. That was the easy part. The hard part was closing down part of Chicago's Loop and lifting the equipment onto the hotel's roof via helicopter.

One weekend this past spring, State and Monroe streets were shut down so that a S61 helicopter, with a lift capability of 8,500 lbs., could lift four lower cells and four upper cells of a four-cell cooling tower onto the roof of the Palmer House. Weighing more than 7,700 lbs. per piece, the helicopter lifted each of the eight pieces onto the roof individually, requiring a two-pilot operation. Once the pieces were in place, Maddock worked with TMI to coordinate the installation of the new cooling tower and connect the new equipment to the existing condenser water piping and cooling tower system.

"Because Palmer House's cooling tower was old and the original manufacturer was no longer in business, the hotel did not want to spend money on costly repairs to fix an outdated machine," said Matt Maddock, president of Maddock Industries. "It made sense for the Palmer House to purchase and install a new cooling tower with expert assistance from TMI."

In order to help the Palmer House justify the capital expense of a new tower, Marley and Maddock conducted a productivity analysis. The analysis, which consisted of an extensive audit of the original system and modeling of the new system, demonstrated how replacing the tower would pay for itself in reduced maintenance and energy savings. The justification for upgrading was there, with more than $60,000 per year in energy savings alone.

Constructed of stainless steel, the new cooling tower is 23 ft. tall and 22 ft. wide and has a life expectancy of more than 25 years. Maddock Industries also outfitted the new tower with variable frequency drives from Yaskawa, an efficiency feature that is expected to save the Palmer House energy.

"The best part about the new cooling tower is that not only will it keep guests cool, it is environmentally sound and will save the hotel money in the long term," said Bob Doessel, vice president of construction operations for TMI.

For more information on Marley Cooling Towers, visit www.marleyct.com/hvac2.asp.

Email
Print
Reprint
Learn RSS

Talkback

We would love your feedback!

Post a comment

» VIEW ALL TALKBACK THREADS

Related Content

Related Content

 

By This Author

There are no other articles written by this author.



SPONSORED LINKS

 
Advertisement
Sponsored Links

More Content

  • Blogs
  • Podcast

Blogs


Sorry, no blogs are active for this topic.

» VIEW ALL BLOGS RSS

Podcast

Senior Editor Amara Rozgus (pictured) speaks with John Suzukida, PE, president of Lanex Consulting LLC, Shoreview, Minn. This conversation is about the role of electricity in the future and zoned heating and cooling.
Cooling People, Not Buildings with John Suzukida, PE
Senior Editor Amara Rozgus (pictured) speaks with John Suzukida, PE, president of Lanex Consulting LLC, Shoreview, Minn. This conversation is about the role of electricity in the future and zoned heating and cooling.
Listen Now | Download MP3 | Subscribe
» VIEW ALL PODCASTS Subscribe Now to HVAC & Building Automation and never miss an episode
Advertisements





NEWSLETTERS
Plug in and get the latest CSE news, trends and industry updates delivered directly to your inbox!

Green Scene
CSE Codes & Standards
CSE NewsWatch
CSE Fire and Life Safety Solutions
CSE Business of Engineering Management Report
CSE Electrical Solutions
CSE HVAC Solutions
Pure Power
CSE Product Showcase
©2008 Reed Business Information, a division of Reed Elsevier Inc. All rights reserved.
Use of this Web site is subject to its Terms of Use | Privacy Policy
Please visit these other Reed Business sites